| Place of Origin: | China |
| Brand Name: | CEC TANKS |
| Certification: | ISO 9001:2008, AWWA D103 , OSHA , BSCI |
| Model Number: | J2016012316 |
| Minimum Order Quantity: | 1set |
| Price: | $5000~$20000 one set |
| Packaging Details: | PE poly-foam between each two steel plates ; wooden pallet and wooden box |
| Delivery Time: | 0-60 days after deposit received |
| Payment Terms: | L/C,T/T |
| Supply Ability: | 60 sets per month |
|
Detail Information |
|||
| Place of Origin | China | Brand Name | CEC TANKS |
|---|---|---|---|
| Certification | ISO 9001:2008, AWWA D103 , OSHA , BSCI | Model Number | J2016012316 |
| Acid And Alkalinity Proof: | Standard Coating Suits For PH3 - PH11, Special Coating Suits For PH1 - PH14 | Elastic: | Same As Steel Sheet , Around 500KN/mm |
| Serive Life: | More Than 30 Years | PH Range: | PH 1 - PH 14 |
| Coating Color: | Dark Blue, Dark Green , White, And Customized | Steel Plates Thickness: | 3mm - 12mm , Depends On The Diameter & Height |
| Easy Yo Clean: | Smooth, Glossy, Inert, Anti-adhesion | Coating Thickness: | 4.0.25mm - 0.4mm, Two Coating Internal And External |
| Highlight: | fire water tank sizing codes,glass fused steel water tank,fire water tank details |
||
A fire water tank is the least used asset on most sites and the one with the least tolerance for failure. It sits full for years, is inspected on a schedule, and is expected to deliver its full volume on a single day with no warning and no second chance. That combination makes it a deceptively difficult specification. Buyers who size it by rule of thumb usually discover the shortfall during an insurer review or a hazard analysis, by which point the foundation has been poured and the volume is fixed.
The engineering question is not how much water the site can store, but how much it can store and still deliver. Those are different numbers, and the gap between them is where most fire water systems underperform. Shijiazhuang Zhengzhong Technology Co., Ltd. (Center Enamel) supplies bolted steel fire water tanks engineered to AWWA D103-09 and configured to NFPA 22 and NFPA 25 requirements, with dedicated reserve arrangements, freeze protection and full documentation for insurer and authority review.
Fire water volume is set by the largest single credible demand multiplied by the duration that demand must be sustained, not by site area or by a multiple of daily process water. Start from the hazard and work forward.
NFPA 22 governs the tank, AWWA D103-09 the bolted steel tank structure, NFPA 25 the ongoing inspection and testing regime, and FM Global or the insurer's own data sheets may add approval and arrangement requirements. They address different questions and all apply.
Most fire water failures are not structural. They are a tank shared with process draw, a frozen riser, a suction that vortices, or water that has stagnated into a biological problem. These are specification items, and they are cheap to get right and expensive to retrofit.
| Design Question | Common Mistake | What Good Practice Requires |
|---|---|---|
| Capacity basis | Sized by site area or a rule of thumb | Largest credible demand multiplied by the required duration |
| Shared service | Process draw taken freely from the fire volume | Permanently piped dedicated reserve that process cannot drain |
| Deliverable volume | Nominal tank volume assumed available | Effective volume above the outlet, below overflow, with vortex allowance |
| Freezing climate | Tank insulated, riser ignored | Tank, riser and exposed piping all protected, with heat input where static |
| Long-term condition | No inspection provision until first audit | NFPA 25 access, drainage and coating condition built into the design |
Every tank delivered by Shijiazhuang Zhengzhong Technology Co., Ltd. (Center Enamel) is engineered against AWWA D103-09 and EN 1090 with finite element verification of shell, roof and nozzle loads, fused at 820-930°C under ISO 9001 and ISO 45001 control, holiday tested at 1500 V across one hundred percent of the surface, and assembled with Grade 8.8 bolts and manufacturer-certified sealant. Fire water tanks are engineered to AWWA D103-09 and configured to NFPA 22, with shell courses, coating systems and roof options selected for the climate and hazard, and supplied with dedicated reserve arrangements, vortex breakers, anti-freeze provisions, NFPA 25 inspection access, seismic and wind design, and a documentation package for authority and insurer review.
"A fire water tank is judged once, on the worst day of the site's life, and only the volume it can actually deliver counts on that day."
Establish the design flow from the suppression system - sprinkler density plus hose streams, or fixed monitor and foam flow - then multiply by the duration appropriate to the hazard classification under NFPA 22. Add any simultaneous process or cooling demand, and confirm the result against the local authority, which may require more than the standard minimum.
Yes, but the fire volume must be protected from depletion. The accepted arrangement is a permanently piped reserve: either a separate fire suction leg or a standpipe that fixes the level below which process draw cannot go. An administrative promise not to drain the tank is not accepted practice.
Protection has to cover the whole system. That means tank insulation where the climate requires it, an insulated and heat-traced riser, protected exposed piping, and in some installations a circulation or heating arrangement that keeps static water from freezing. Insulating the tank alone leaves the riser as the failure point.
Yes. Volume, shell thickness, coating, roof type, freeze protection, suction arrangement, level indication and inspection access are all configured to the hazard classification, the local authority requirement and the site climate, and the drawings are issued for authority and insurer review before manufacture.